EDF - Combined Cycle Gas Fired Station


The Veolia Water Technologies’ entity OTV DBI (Design & Build for Industry) was chosen for the construction of a turnkey unit for the production of process water for the power plant (studies, design, manufacturing, installation and commissioning).

Project Background

Key Figures EDF Bouchain
Pre-treatment for cooling tower make up water treatment: 820 m3/h max - Demineralization: 2 x 14 m3/h - Guaranteed discharge (from RO concentrate...


EDF was building a new power plant at its site in Bouchain. This 550MW Combined Cycle Natural Gas fired Station was a technological first and will aim to meet the electricity consumption peaks in the network, with maximum energy efficiency. The project is managed by the Thermal Engineering Centre of EDF.

The Veolia Water Technologies’ entity OTV DBI (Design & Build for Industry) was chosen for the construction of a turnkey unit for the production of process water for the power plant (studies, design, manufacturing, installation and commissioning).

 

The Client's Needs


Produce filtered and softened water to supply the cooling tower.
 
  • Produce demineralized water for the Combined Cycle Gas steam production.
  • Dewater the sludge from the softening process.
  • Use Process Units that can operate in "on/off" mode and achieve the performance in a short time so the plant can face the power consumption peaks with great responsiveness.


Project & Technology Solutions


Actiflo® Softening: This process combines in a single, compact processing unit clarification operations and softening to reduce the hardness of the water and remove suspended solids.

Multi-Media Filtration: This step ensures the removal of suspended solids.

Aquadem™ Solution: Demineralization service that uses ion exchange resin technology to produce high quality purified water without onsite regeneration.

 

Benefits


Actiflo® Softening:
  • Small footprint – very high rate ballasted settling.
  • Chemical precipitation reaction accelerated by the Turbomix™ reaction vessel.
  • Starts / stops quickly. Quality water made in less than 60 minutes guaranteed from a standby mode.
     
Coupling Multi Media Filtration / Reverse Osmosis (RO):
  • Increased risk control of biofouling and post-precipitation of the RO membranes.
     
Aquadem™ Solution:
  • Ease of operation - no regeneration equipment.
  • Lower investment costs.
  • Respect for the environment and safety thanks to the absence of chemicals and their related waste.